Ottawa’s Project Management Policies

The focus of our services is interior design and renovation for commercial premises which include shopping malls, hotels, offices and other spaces meant for conducting businesses.

As a general rule of thumb, for units that is lesser than 1000sqft, it is advisable for tenants to start discussing the details of the project a month in advance. Confirmation of the project should take place at least 2 weeks in advance before taking over the keys for renovation. This is to facilitate off-site fabrication and reduce construction time on site.

 

SCHEDULE OF WORKS DURATION
SPACE PLANNING/DESIGN & CONTRACT CONFIRMATION
To confirm the specification of the project
2 weeks to 1 month
QUOTATION & CONFIRMATION OF PROJECT
Summing up of material & construction fees
3 to 10 days
SUBMISSION
Submission of drawings to building management for approval
3 days to 2 weeks (dependant on management)
CONSTRUCTION
Actual construction starts at site
Min 4 weeks (depends on the complexity of works
ELECTRICAL TESTING & OTHERS 2 to 12 weeks

* Every project is different – even the simplest project has its uncertainties. Our information is designed to give you a general idea of the development of a commercial renovation.